Immanuel Trinity Lutheran Church
Fond du Lac, WI
Home
Our Vision Statement
Our Mission Statement
What We Believe
Meet Our Staff
Worship Services
Ministries
Missions / Outreach
Publications / Articles / Meditations
Calendar
Council Minutes
2009 Church Council
Weekly Bulletins
Building for the Future
Photo Gallery
Prayer Requests
Links
Library
Contact Info
BUILDING FOR THE FUTURE

 

 

 

 

EVENTS AND STATUS LEADING US ON THE JOURNEY

This review is presented to keep everyone informed of the efforts taken on by the Long Range Planning Committee that really started in 1990 and the successive Facilities Task Force Committee formed in 2000. There may be some of our members who have forgotten or are not aware of the circumstances leading up to future planning of Immanuel-Trinity. This would be the situation for the newer and most recent members who have joined us. [Scroll to bottom for recent updates] 

Building for the Future

Early 1999..... Long Range Planning Committee surveyed the Congregation of Immanuel-Trinity. Results asked for more space and handicap accessibility.

November 29, 1999..... Long Range Planning Committee held a planning Summit. What we envision as a church community, and to determine what steps are needed to accomplish those objectives. Three action teams were formed.

April 29, 2000..... A Re-Summit. The action teams compiled information. Input from parishioners in attendance; top priority was to remodel and expand current facilities to make it a user friendly facility or build a new facility.

June 4, 2000..... Outcome of the Summits resulted in the Facilities Task Force committee organized.

July 17, 2000..... An agreement with Stodola-Maas Construction was entered into acting as consulting construction manager.

November 2000..... Facilities Task Force committee members investigated the needs of all the various ministries of our parish for an in-depth understanding of what their needs are in carrying out those ministries. On the extensive input from that effort a programming need may be prepared for our facilities.

January 2001..... Seven architectural firms were contacted. Four selected for interviews.

February 2001..... Excel Engineering was selected.

March 2001..... "Existing Conditions Report" of our facilities completed by Excel Engineering.

April 23, 2001..... Additional input from representatives of our various ministries to prepare a programming needs assessment was gathered by Excel Engineering.

May 14, 2001..... Draft of our programming needs reviewed with Excel Engineering.

June 18, 2001..... Excel Engineering presented the programming needs and developed schematic plans for renovation of present facility with two options and included a schematic plan for building new.

September 2001..... Congregation was presented with schematic plans in a mailing and series of forums so members of the parish had the opportunity to provide feedback.

April 7, 2002..... Special Congregational to vote; Should we renovate the present facilities with one of the two options or build new at a new site? The Congregation chose to build new at a new site.

Summer 2002..... The Facilities Task Force committee then embarked on finding a new site. From the 12 sites considered a site in the Wisconsin BusinessPark and offered for sale by Sam Hendrickson was selected.

December 23, 2002..... A final counter offer to purchase was accepted with contingencies with one being the approval of the Congregation of Immanuel-Trinity.

December 2002 - March 2003..... Kairos and Associates, Inc. were contracted to conduct a Feasibility study to determine our financial readiness for planning and moving forward with the facility needs. Results recommended that we should proceed.

January - February 2003..... Information on the selected site was provided to all Congregation families by mailings and in a series of forums so members of the parish had the opportunity to be completely informed.

March 13, and 16, 2003..... At special Congregational meetings the Congregation voted to approve (Part 1 of the Ballot) to purchase the property. The Congregational vote (Part 2 of the Ballot) affirmed that we would use existing funds rather than borrowing them from a bank to purchase the property.

April 15, 2003..... Closing was completed. Immanuel-Trinity has a new site for our journey to the future.

June 9, 2003..... The first function at the new church property was a Facilities Task Force committee meeting along with thier picnic.

July 22, 2003..... Kairos and Associates, Inc. contracted with to lead us in the Capital Fund appeal.

September 8, 2003..... The existing programming needs were reviewed and revised and were be presented to Excel Engineering for preliminary site study and space allotments.

September 9, 2003..... A New Contract with Excel Engineering for architectural and engineering services was negotiated. Existing contract with Stodola-Maas Construction for consulting construction manager approved.

October 20, 2003..... Excel Engineering used the needs analysis provided from our revised programming assessment and prepared a schematic site plan design, site analysis, and details for our future facility.

December, 2003..... A Kairos and Associates consultant and an executive team formed of several congregation members organized twelve teams with each taking responsibility for some part in the capital appeal drive with a theme "Building for the Future". 

February 22, 2004..... The capital appeal "Building for the Future".  packets were distributed to all members in attendance that Sunday and delivered to members not in attendance or mailed if not in the immediate area.

March 28, 2004.....Was commitment Sunday and a festive day to offer pledges to the "Building for the Future" campaign.

April 2004.....While awaiting the results of the capital appeal the Facilities Task Force committee continued working on the best action to take concerning building on the new site.  It was determined construct the main buildings in phases.  The first being Phase I would include preparing the site, constructing a utility building, Family Life Center, kitchen, youth room ,offices and several class/meeting rooms.

June 2004..... After numerous forums and through a special mailing, information was provided about Phase I to all congregational members for a vote. The vote gave approval to borrow funds for the Phase I project.

August 29, 2004..... Land Dedication service ceremony on the  property purchased in 2003.

September 2004.....The site plan, building elevations and floor plans were approved in concept by Facilities Task Force committee. Specific building details and construction drawings began. 

November 2004.....The final site layout was submitted to the city of Fond du Lac with necessary permits obtained. The site was staked out; soil borings were taken for Phase I and at areas for the future Phase II and III. 

Later part of November 2004..... Site preparation and grading began with the clearing of trees, brush, stripping of the topsoil and forming of the building pad.

December 2004.....The slab was poured for the utility building that will be contructed by volunteers as soon as weather permits.

February 7, 2005.....Construction drawings were completed by Excel Engineering for Family Life Center and bidding process began.

February 23, 2005.....Deadline for bids from sub-contractors  with an interest in bidding on the many trades associated with the construction  of the Family Life Center were due to our Construction Manager Stodola Maas who  also acts as a Constructor.

March 7, 2005....The  Facility Task Force committee reviewed  the cost of construction from the compiled bids.  By a vote of the committee it was agreed  to proceed with the Phase I project with the Church Council's approval.

March 8, 2005....At a special Church Council meeting the Facility Task Force recommendation was presented and discussed. It was unanimously agreed upon by a vote to give the Construction Manager a letter of intent to lock in the bids and proceed with the project.

April  4,  2005....Site pre-construction began again with heavy equipment brought to the site to begin excavation for stormwater conveyance piping to the retention pond from the parking area.

May 1,  2005....Immanuel-Trinity Lutheran Church held a groundbreaking ceremony for the Family Life Center at the new site on 20 Wisconsin American Drive. The Family Life Center will include more than 18,000 square feet. More than $625,000 has been pledged for the project which has an approximate cost of $2.2million. Construction actually began last month as weather was in our favor, and should be complete by late 2005.

May 21, 2005.....The utility building that will be constructed by volunteers was started. The first task was setting the framing and sheathing the walls.

June 4, 2005.....Volunteers at this work day placed the roof trusses and started sheathing the roof.

June 11, 2005.....Volunteers at this work day continued sheathing the roof placed tar paper on roof.

June 18, 2005.....The utility building volunteers at this session started roofing and constructed the gable to hip framing details.

July 9, 2005.....Roofing of the utility building was almost completed by the volunteers at this session and tylar warp was put on side walls. Extreme heat prevented the work from being completed as damage to the roofing might happen.

August 6, 2005.....The utility building roofing was completed  and vinyl siding was started at this session.

August 20, 2005.....The utility building volunteers completed the project except for interior work that would consist of electrical and a bit of carpentry for arranging the storage and use ideas.

November 15, 2005.....The entire Phase I project moved along ahead of schedule since the start of building the Family Life Center in April 2005. Delivery of furnishings will be allowed after December 1, 2005. 

December 17, 2005.....After approximately 8 1/2 months the Family Life Center was completed. Inspection by the city inspector done December 12, 2005. Immanuel-Trinity was given occupancy. Some work was needed to complete the sound and the video projection systems which were partially installed.

January 3, 2006.....Beginning today the Family Life Center will be staffed by volunteers, Monday thru Thursday 8:30 a.m.-4:30 p.m., who will greet visitors and accept deliveries.

February 4, 2006.....The first Blended worship service(5:30 p.m.) was held at the Family Life Center.

February 5, 2006.....The first Sunday Worship service (11 :00a.m.) was held at the Family Life Center.

March 12, 2006.....The Senior High Youth hosted the very first Spaghetti dinner and Talent show in the Family Life Center to the delight of all who attended.

March 26, 2006.....Members of Immanuel-Trinity were invited to the second annual Appreciation Dinner held in the new Family Life Center.

April 23, 2006.....Formal dedication of the Family Life Center that was preceeded with an open house and tours offered to the whole community.

 Updates and brief information can be viewed at Progress of the Family Life Center. an album in the photo gallery.

Updates will continue---Also Check the photo gallery

Web site design by Faithwebsites.com